Skip links

NEWS

Phase-2: December Update

by Radha Kunjabihari das | Dec 18, 2021 | Announcements

Rough Carpentry framing is complete for third floor office rooms and mechanical room on first floor

Phase-2: December Update

by Radha Kunjabihari das | Dec 11, 2021 | Announcements

Concrete infill at stair treads STR 1,2,3 are completed. Roofing ISO, TPO and flashing 98% is completed – remaining 2% are related to electrical and plumbing penetrations.

Rough carpentry at first floor kitchen and stairwell enclosures are progressing Mechanical duct work are progressing

This temple will serve the community for many generations to come. Be a part of this incredible legacy.

Phase-2: November Update

by Radha Kunjabihari das | Nov 13, 2021 | Announcements

First Floor concrete has been laid out and Second Floor concrete is 50% complete.Blown in insulation on roof parapet is done, roof ISO and TPO membranes are at 60% completion.Curb at Skylite is finished. Roofing work of Sri Sri Radha madam is under progress. First picture is from the south side and second picture is from North.

Phase-2: October Update

by Radha Kunjabihari das | Oct 16, 2021 | Announcements

RTU penetrations and zone dampers are 60% complete. Exterior sheathing is 70% done.

Phase-2: October Update

by Radha Kunjabihari das | Oct 9, 2021 | Announcements

The dream of Naperville community to build a grand temple for Sri Sri Radha Syamasundara is slowly but steadily being realized. In this phase of construction, work is progressing at a steady pace. Framing of stairs #3 and roof access have been completed. Deck and parapet at stairs are also done.

Phase-2: September Update

by Radha Kunjabihari das | Sep 25, 2021 | Announcements

Perimeter parapet roof studding is 85% complete. Perimeter exterior wall framing is 70% done. Underground plumbing penetrations have been finished along with steel framing for all the stairs which is 95% done.

Phase-2: September Update

by Radha Kunjabihari das | Sep 17, 2021 | Announcements

Construction of our much awaited temple is progressing at a smooth pace.Currently, the elevator work is in progress. Approval of dual gas service for existing structure throughout the winter season was obtained. Perimeter parapet wall and kicker base have been completed.

Phase-2: September Update – 1

by Radha Kunjabihari das | Sep 12, 2021 | Announcements

During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as well.

Phase-2: July Update – 4

by Radha Kunjabihari das | Jul 30, 2021 | Announcements

Construction is going on as per schedule. Steel framing work will continue for a few more weeks.

Phase-2: July Update – 3

by Radha Kunjabihari das | Jul 23, 2021 | Announcements

Construction Update: July 19 th

The reinforced concrete foundation for the main building is in place. Steel framing is currently in process.

This website uses cookies to improve your web experience.